Downtown Street Reconstruction
Overlay and Utility Improvements
San Jacinto and Lavaca Streets
Summary
The projects will provide for the reconstruction, pavement overlay, and
water and wastewater improvements of various downtown streets.
Status
- San Jacinto Street: Construction is scheduled for spring 1997
- Lavaca Street: Construction is to start mid-September 1996 and
is expected to take 6 months to complete.
Description
Planned improvements include repair of pavement failures, construction of
concrete bus pads, construction of sidewalk ramps, and overlay and striping
of the streets, in addition to replacement of old and/or shallow water and
wastewater lines. Construction limits for each of the streets are:
- San Jacinto Street: 6th - 9th
- Lavaca: 11th - MLK
Basic Data
Project Manager: Sondra Creighton, P.E., Department of Public Works
and Transportation, 440-8444
| Construction
Estimate | Predominant Funding
Source |
| San Jacinto Street | $617,292 | C.I.P. |
| Lavaca Street | $1,444,452 | C.M.T.A. |
Revised January 9, 1997