skip to main content
Austin City Connection logo; link back to Austin City Connection home page
 
Options

Directory | Departments | FAQ | Links | Site Map | Help | Contact Us

Seaholm Power Plant Reuse

Logo derived from the facade of Seaholm Power Plant

Summary

The Seaholm Power Plant sits on an eight-acre site on the north shore of Town Lake. The plant no longer generates power for the City. Private sector groups, including the R/UDAT Team and Implementation Committee, have recommended that Seaholm be adapted for civic or cultural uses. In 1996 the City Council resolved to preserve Seaholm for a major public use its after decommissioning and remediation is complete. Field activities should be complete by the end of November 2001, to be followed by four to six months of closure report preparation and report review by the Environmental Protection Agency and the Texas Natural Resource Conservation Commission.

Currently the on-site decommissioning and remediation activities completed to date include: the removal of all equipment from the Turbine Generator Building, Water Intake Structure and the old Pump Room Eagle Construction is 98% complete with the removal of asbestos containing material from the inside of number 5 and 6 boilers, 45% complete with removal of asbestos containing material from 7 and 8 boilers and 85% complete with removal of asbestos containing material from the inside of no. 9 boiler. Lead based paint abatement of stacks 5, 6, and 7 are 100% complete. Repainting of stacks 6 and 7 are 100% complete and re-painting of stack 5 is 75% complete. Scaffolding is being erected around the number 8 and 9 stacks to facilitate abatement of lead-based paint and repainting. PCB and mercury contamination removal will begin during the week of July 9, 2001. Because of changeorders executed during the project and delays encountered by Eagle Construction, the revised schedule end date for the field activities at Seaholm Power is now November 2001.

Status

In November 1999, City Council passed a resolution directing the City Manager "to make recommendations outlining next steps for decommissioning the Seaholm Power Plant and soliciting proposals for the reuse of the plant." In December 1999, the City hired Sherry Kafka Wagner, public attractions consultant, to help identify and execute these "next steps".

In concert with Ms. Wagner's recommendations, a City Manager's Office memo was issued in March 2000 that recommended that, prior to the City's soliciting for proposals, an urban design and redevelopment master plan be generated to guide the City in making decisions about the entire district around the power plant. This master plan will recommend: type(s) and location(s) for future visitor parking for Seaholm, an intermodal transportation network with possible light rail and intercity rail connections, and how the district and the Seaholm Reuse Project may best link and integrate the adjacent downtown and parkland areas.

In June 2000 Council authorized the hiring of ROMA Design Group to create this master plan which will make recommendations about the urban design and economic redevelopment of the area surrounding the power plant facility. This process began in August, with the development of "framework sketch concepts". A series of stakeholder work sessions have since taken place, and a second, more fleshed out concept master plan is currently in the works for stakeholder review likely sometime in November.

The City has also completed the historical documentary photography for the three Seaholm buildings that have been identified as eligible for listing on the National Historic Register: the Turbine Building, the Water Intake Structure and the Fuel Oil Building. This photography documents the plant with all its equipment in place, prior to the final demolition and remediation phase that began in July 2000. This photographic collection will be made publicly available at the Austin History Center collection later this fall.

Description

The Seaholm Power Plant, built between 1950 and 1958, faces Town Lake on West César Chávez Street. It is composed of five gas/oil generation units (100 megawatts total when it functioned) and no longer generates power. The building features a towering turbine room 110 by 235 feet, with clerestory windows above flanking aisles, and a 65-foot-high ceiling. Two lower floors contain an additional 75,000 square feet. In all, the building has more than 110,000 square feet of useable floor area. An electric utility substation, transmission and distribution facilities, and a utility microwave communications center are also located at Seaholm.

A number of planning efforts have recognized Seaholm's significance and potential for adaptive reuse. The City of Austin's 1984 Historic Resources survey targeted Seaholm for its highest priority rating of building to be preserved. The City's Town Lake Park Comprehensive Plan suggests that the plant be "converted into an activity center complementary to the area." In the fall of 1997, the R/UDAT Revisited Team reiterated its earlier support for Seaholm's cultural reuse.

Basic Data

  • City Contacts:
    Andy Ramirez, Austin Energy, 322-6479
    Jana McCann, Transportation, Planning, & Sustainability Department, 974-6096
  • Public-Private Partnership:
    Seaholm Reuse Planning Committee, Leslie Pool, chair, 346-8717

Map of Seaholm Area

Revised May 7, 2001


Back to the July 2001 Downtown Report

Back to the Downtown Redevelopment


Official Seal of the City of Austin
Austin City Connection - The Official Web site of the City of Austin
Contact Us: Send Email or 512-974-6418.
Legal Notices | Privacy Statement
© 1995 City of Austin, Texas. All Rights Reserved.
P.O. Box 1088, Austin, TX 78767 (512) 974-2000