Shoal Creek Flood Repairs
Summary
This phase of the project is a gabion wall failure near West Avenue and Shoal Creek.
Status
Construction is underway; the project is 25% complete.
Description
The failed gabion section will be removed and replaced with approximately 150 lineal feet of concrete wall. Approximately 150 feet of sidewalk will also be installed connecting a hike-and-bike trail from the east end of the Energy Management Building, southeasterly to the existing sidewalk.
Basic Data
Project Contact: Ginger Daniels, P.E., Department of Public Works and Transportation, 499-0145
Project Manager: Walter Boettcher, P.E., Department of Public Works and Transportation, 499-7220
Construction Start Date: September 1995
Completion Date: January 1996
Estimated Cost: $350,000
Revised Dec. 28, 1995