Shoal Creek Flood Repairs
Summary
This phase of the project is a gabion wall failure near West Avenue and
Shoal Creek.
Status
Construction is underway; the project is 99% complete. Completion is
expected in June 1996.
Description
The failed gabion section will be removed and replaced with
approximately 150 lineal feet of gabion wall. Approximately 150 feet of
sidewalk will also be installed connecting a hike-and-bike trail from
the east end of the Energy Management Building, southeasterly to the
existing sidewalk.
Basic Data
Project Manager: Walter Boettcher, P.E., Department of Public Works
and Transportation, 499-7220
Construction Start Date: September 1995
Completion Date: June 1996
Estimated Cost: $350,000
Revised June 26, 1996
|