Street Reconstruction, Overlay and Utility Improvements

Congress Avenue, Brazos, Colorado, and San Jacinto Streets


Summary

The project will provide for the reconstruction, pavement overlay, and water and wastewater improvements of various downtown streets.

Status

  • Congress Avenue: Construction is underway.
  • Colorado Street / Brazos Street: The design is essentially complete; bidding is on hold pending completion of Capital Metro's bus route plan for the downtown area.
  • San Jacinto Street: The design is complete; construction is scheduled for fall 1996.

Issues

Colorado and Brazos will be bid following completion of Capital Metro's bus route plan.

Description

Planned improvements include repair of pavement failures, construction of concrete bus pads, construction of sidewalk ramps, and overlay and striping of the streets, in addition to replacement of old and/or shallow water and wastewater lines. Construction limits for each of the streets are:
  • Congress Avenue: César Chávez - 11th
  • Brazos Street: César Chávez - 11th
  • Colorado Street: César Chávez - 11th
  • 2nd Street: Congress - Trinity
  • 9th Street: Congress - San Jacinto
  • San Jacinto Street: 6th - 9th

Basic Data

  • Project Manager: Sondra Creighton, P.E., Department of Public Works and Transportation, 440-8444

    Construction EstimatePredominant Funding
    Source
    Congress Avenue$1,600,000C.I.P.
    Brazos Street$1,100,000C.M.T.A.
    Colorado Street$400,000C.M.T.A.
    San Jacinto Street$400,000C.I.P.

    Revised June 26, 1996

  • Official Seal of the City of Austin
    Austin City Connection - The Official Web site of the City of Austin
    Contact Us: Send Email or 512-974-6415.
    Legal Notices | Privacy Statement
    © 1995 City of Austin, Texas. All Rights Reserved.
    P.O. Box 1088, Austin, TX 78767 (512) 974-2000